Decision Maker: Planning Committee
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Installation and operation a of a renewable
energy generating station comprising ground-mounted photovoltaic
solar arrays and battery-based electricity storage containers
together with substation, point of connection mast, switchgear
container, inverter/transformer units, Site access, internal access
tracks, security measures, access gates, other ancillary
infrastructure and landscaping and biodiversity enhancements,
Church Farm, Washpit Lane, Barlestone
Application for installation and operation of a renewable energy generating station comprising ground-mounted photovoltaic solar arrays and battery-based electricity storage containers together with substation, point of connection mast, switchgear container, inverter/transformer units, site access, internal access tracks, security measures, access gates, other ancillary infrastructure and landscaping and biodiversity enhancements.
An objector, the applicant and a representative of Nailstone Parish Council spoke on this application.
It was moved by Councillor Bray, seconded by Councillor Gibbens and
RESOLVED –
(i) Permission be granted subject to the conditions contained in the officer’s report and late items;
(ii) The Planning Manager be granted powers to determine the final detail of planning conditions
(iii) The Planning Manager be requested to review landscape screening proposed prior to issuing the decision.
Report author: Chris Brown
Publication date: 04/08/2022
Date of decision: 02/08/2022
Decided at meeting: 02/08/2022 - Planning Committee
Accompanying Documents: