Installation and operation a of a renewable energy generating station comprising ground-mounted photovoltaic solar arrays and battery-based electricity storage containers together with substation, point of connection mast, switchgear container, inverter/transformer units, Site access, internal access tracks, security measures, access gates, other ancillary infrastructure and landscaping and biodiversity enhancements, Church Farm, Washpit Lane, Barlestone

Decisions:

Application for installation and operation of a renewable energy generating station comprising ground-mounted photovoltaic solar arrays and battery-based electricity storage containers together with substation, point of connection mast, switchgear container, inverter/transformer units, site access, internal access tracks, security measures, access gates, other ancillary infrastructure and landscaping and biodiversity enhancements.

 

An objector, the applicant and a representative of Nailstone Parish Council spoke on this application.

 

It was moved by Councillor Bray, seconded by Councillor Gibbens and

 

RESOLVED –

 

(i)            Permission be granted subject to the conditions contained in the officer’s report and late items;

 

(ii)          The Planning Manager be granted powers to determine the final detail of planning conditions

 

(iii)         The Planning Manager be requested to review landscape screening proposed prior to issuing the decision.

Report author: Chris Brown

Publication date: 04/08/2022

Date of decision: 02/08/2022

Decided at meeting: 02/08/2022 - Planning Committee