Issue - meetings

25/00347/FUL - The White Swan, 47 High Street, Stoke Golding

Meeting: 13/01/2026 - Planning Committee (Item 304)

304 25/00347/FUL - The White Swan, 47 High Street, Stoke Golding pdf icon PDF 432 KB

Application for extension to existing public house, change of use of existing garden land for glamping use and associated works.

 

Late items received after publication of agenda:

 

Amended Conditions

 

Since publication of the report several amendments have been made to the proposed planning conditions, the updated condition list is provided below

 

1.    The development hereby permitted shall be begun before the expiration of three years from the date of this permission.

 

Reason: To comply with the requirements of Section 91 of the Town and Country Planning Act 1990, as amended by the Planning and Compulsory Purchase Act 2004.

 

2.    The development hereby permitted shall not be carried out otherwise than in complete accordance with the submitted application details, as follows:

 

·         Site Location Plan, Drg No. 24 079 DL0101 P1 (submitted: 31.03.2025)

·         Site Plan as Proposed, Drg No.24.079 DK0001 P3 (submitted: 23.10.2025)

·         Site Plan as Proposed Detail, Drg No. 24.079.DK0002 P5 (submitted: 23.10.2025)

·         Proposed Cellar Floor Drg No.24.079.DK0005 P1 (submitted: 31.03.2025)

·         Proposed Ground Floor Drg No.24.079.DK0003 P1 (submitted: 31.03.2025)

·         Proposed First Floor Drg No.24.079.DK0004 P1 (submitted: 31.03.2025)

·         Proposed Elevations (East and South)- Drg No.24.079.DK0006 P1 (submitted: 31.03.2025)

·         Proposed Elevations (West and North) -Drg No.24.079.DK0007 P1 (submitted: 31.03.2025)

·         Proposed Floor Plans and Elevations Kitchen/Shower and Bar/WC Drg No.24.079.DK0009 P1 (submitted: 31.03.2025)

·         Proposed Floor Plans and Elevations, Tents, Dining Dome, Bin and Cycle Store Drg No.24.079.DK0010 P2 (submitted: 08.08.2025)

 

Reason: To ensure a satisfactory form of development in accordance with Policies DM1 and DM10 of the Site Allocations and Development Management Policies Development Plan Document (2016).

 

3.    No development above slab level shall commence on site until representative samples of the types and colours of materials to be used on the external elevations of the buildings hereby permitted have been deposited with and approved in writing by the Local Planning Authority, thereafter the scheme shall be implemented in accordance with those approved materials.

 

Reason: To ensure that the development has a satisfactory external appearance and preserves the special interest of the site in accordance with the requirements of Section 66 and 72 of the Planning (Listed Buildings and Conservation Areas) Act 1990 and in accordance with Policies DM11 and DM12 of the adopted Site Allocations and Development Management Policies Development Plan Document (2016) and the National Planning Policy Framework (2024).

 

4.    No development above slab level shall commence on site until a schedule of hard and soft landscaping works, including boundary treatments, for the site, including an implementation scheme, has been submitted in writing and approved in writing by the Local Planning Authority. The scheme shall thereafter be carried out in full accordance with the approved landscaping scheme.

 

The soft landscaping scheme shall be maintained for a period of five years from the date of planting. During this period any trees which die or are damaged, removed or seriously diseased shall be replaced by trees or shrubs of the same size and species as those originally planted unless otherwise agreed in writing by the Local Planning Authority.

 

Reason: To ensure that the development  ...  view the full agenda text for item 304

Minutes:

Application for extension to existing public house, change of use of existing garden land to glamping use and associated works.

 

The agent spoke on this application.

 

Whilst in support of the officer’s recommendation that permission be granted, it was requested that condition 9 be amended to prevent fireworks in addition to preventing bonfires. It was moved by Councillor Allen, seconded by Councillor Bools and unanimously

 

RESOLVED –

 

(i)            Permission be granted subject to:

 

a.    The conditions outlined in the officer’s report and late items;

 

b.    An amended condition 9 to read:

 

“There shall be no bonfires or release of fireworks permitted on the site”.

 

(ii)          The Head of Planning be granted authority to determine the final detail of planning conditions.